EXECUTION, IN CONTEXT

Read the dependencies.
Not just the date.

Explore what has to come together for accepted nuclear output. Start with a simple exercise, then examine the conditional reference results.

CHOOSE A CONTEXTIndependent illustrative analysis

ALVA · Two-unit uprate reference

REFERENCE v0.1

A hypothetical site with two PWR units. The modeled endpoint is both units accepted for incremental output, not the first unit or the start of an outage.

REFERENCE SCOPE

One site. Both units.

600 net MWe is an analyst assumption.
HYPOTHETICAL · NOT CALIBRATED

Numerical implementation QA passed; this is not empirical validation or an ALVA- or utility-calibrated model.

An exercise, not a simulation

FICTIONAL DEPENDENCY EXERCISE

What is still missing?

See what holds the handoff—the point where all required inputs come together.

TEACHING MODE

Explore which prerequisite holds the handoff. Load a preset, then change individual checkboxes. Checked means assumed available in this exercise.

No delay duration is calculated here.

Follow these steps to watch demo

  1. Load a preset

    Choose a preset below. It loads the starting selection for all five checkboxes.

  2. Toggle prerequisites

    Check or uncheck an item. Checked means assumed available—not verified.

  3. Read the result

    See which missing inputs hold the handoff. Every prerequisite is required.

  4. Open the separate preserved view. Demo selections do not change its outputs.

How this works

Presets load a starting configuration. Each preset sets all five checkboxes. Pressing “Missing equipment” again reloads that configuration; it does not turn the preset off. Use a checkbox to change one prerequisite.

Every prerequisite is required. The handoff, also called a “join,” is where all required inputs come together. A selected item cannot substitute for a missing one. If two items are missing, selecting just one still leaves the handoff held by the other.

Five binary controls allow 32 possible checkbox configurations—not 32 simulations or real-world project states. Reference results come from separate preserved runs. Toggling these boxes does not rerun them or calculate real delay.

Load a starting configuration
Select the five fictional prerequisites
TRY IT

Select Equipment to clear this block, then uncheck Qualified workforce to see a different hold.

THE TAKEAWAY

A qualified crew cannot install equipment that is not available. For a two-unit uprate, engineering, equipment, execution and outage interfaces have to come together.

All checkbox states are fictional. They do not describe any of the companies shown, and they do not change the reference snapshots or schedule screens.

RELATED SYNTHETIC BRIEFING

Inside the outage window.

A separate synthetic demo shows how a deterministic schedule checker, such as the PRISM method described in a public 2019 DOE report, could supply outage-readiness evidence to WIMS for reactor coolant pump replacement, steam generator replacement and existing turbine centerline work. Fictional unit and data. No PRA output, calibrated forecast or partnership is implied.

Open the outage diagnostic demo   Why PRISM

BOUNDARIES BEFORE CONCLUSIONS

What this does not establish.

Implementation is not validation.

Reference results and schedule screens use analyst-selected assumptions. Numerical checks can establish that code implements a specification; they cannot establish that the specification describes a real project.

Fermi v0.2: main-agent reconstruction passed. Separate independent review is incomplete.

ALVA reference boundaries

    These are selected preserved reference results and evidence-review contexts, not the full public engine. The five-checkbox exercise does not reproduce any model. No investment, procurement, licensing or schedule commitment should be based on this explorer.

    PUBLIC EVIDENCE

    Trace the context. Keep the distinctions.

    CUTOFF · 13 SEP 2026

    Sources establish public statements and regulatory context—not numerical inputs, intervention benefits or model accuracy. No company endorsement is implied.

    THE WIMS ORGANIZING LENS

    Twelve dimensions.
    No invented scores.

    These canonical labels organize questions about execution. They are not a scored assessment and are not all fully modeled in either reference.

    The teaching prompts below explain the lens; they do not assert project conditions or model coverage.

    You don’t fight the hill.
    You change the gearing.